Capital Campaigns

2018 Building Addition

The Central High School Foundation is proud to announce our Central High School East Addition Capital Campaign.

Project Description:

A 51,000 square foot addition to the east side of the building with all associated site, access walk ways, services, and utilities. A single story, connection link (1,200 square feet) within the existing Central High School facility. 

The timeline for the project is as follows:

  • Design to construction documents – Nov. 2016 to Spring 2017
  • Groundbreaking - Thursday, June 22, 2017
  • Addition construction start – Summer 2017
  • Addition substantial completion – Fall 2018
  • Final Addition completion – Winter 2018
  • Repurposing of existing building space to begin upon completion of new Addition

Below is a timelapse video of the project beginning July to September 14, 2017 

Click on the pictures below to see floorplans and street-level renderings of the new structure.

side view-min building addition street level2 thumbnail-compressor building addition street level thumbnail-compressor building addition level3 thumbnail-compressor building addition level2 thumbnail-compressor building addition level1-thumbnail compressor building addition plazalevel thumbnail-compressor watercolor rendering-compressor